Thousands of residents across Kent are experiencing severe water supply disruptions following an instrument failure at a local treatment works, impacting over 7,000 properties.
South East Water (SEW) confirmed over 7,000 properties in the Tunbridge Wells area face low pressure, intermittent supply, or a complete loss of water.
The company deployed tankers to boost drinking water storage levels and initiated bottled water deliveries to customers on its priority services register.
Bottled water stations opened in Tunbridge Wells and will remain operational until 8 PM on Sunday, providing essential relief to affected households.
SEW stated supplies were expected to begin returning on Sunday evening at the earliest, issuing an apology to its impacted customers.
Steven Benton confirmed the water treatment works were "now stable," addressing the immediate cause of the disruption.

Now stable.

Steven Benton
Benton added that low storage levels from this incident, combined with high demand, prevent the pumping of water to some areas, particularly those on higher ground.
He stated tanks must replenish to ensure a stable, continuous flow, indicating a prolonged recovery period.
The immediate impact became evident as Mike Martin reported the rugby club station had run out of bottled water, depleting emergency supplies rapidly.
This incident marks the latest in a series of failures that previously led Ofwat to order SEW to spend £30.5 million on infrastructure improvements.
Ofwat imposed a £30.5 million penalty on SEW after investigations into previous supply interruptions, revealing a pattern of operational shortcomings.
The redress package included a £22 million fine for water supply failures between 2020 and 2023, affecting over 286,000 people across the region.
A second probe by Ofwat commenced after further supply interruptions between November and January, leaving up to 70,000 homes without water.
Customers received advice to boil their water for nine days after supply returned following the November incident, detailing the public health implications of these failures.

Customers received advice to boil their water for nine days after supply returned following the November incident.

Ofwat
A third investigation began after Moody’s downgraded SEW’s credit rating in May, a move that breached a critical licence condition.
These repeated operational issues and regulatory actions place significant pressure on SEW's leadership.
The company announced its chair had departed, and its chief executive would also leave following earlier failures, indicating a major change at the top.
The ongoing disruptions reveal a critical vulnerability in the region's water infrastructure, raising questions about long-term resilience and investment strategies.
The public, facing repeated inconveniences and health advisories, continues to demand accountability and reliable service from their utility provider.